SEM, on behalf of SA Power Networks, will start on preliminary work on 11 January 2016 just south of the tram line. The work will be done between 7pm to 6am 5 days a week, with Saturdays as required to cause the least disruption to traffic. SAPN engaged SEM for the civil works, i.e.
trenching and conduits laying. A separate contractor will subsequently pull
through cables and eventually remove the stobie poles. Undergrounding power
lines is scheduled to be completed by August/September 2016.
Council is making good progress in the design for the streetscape
upgrade that will follow the completion of the works.