- The culvert for the Brownhill Creek diversion. Night works for this will continue from 28th Dec to 31st Dec 2012, continuous construction activity will occur.
- SA Power Networks trenching in Aroha Tce, Lyons Pde and Railway Tce South.
- Overhead power lines installed in foster St.
- Reconfiguration of the Victoria St pedestrian crossing.
- Removal of the rail tracks (7am to 10pm) from the 9th Jan 2013
- The continuation of the Cromer Pde sewer installation
- Completion of the site storage at Wayville Showgrounds.
- Demolition of houses in Devon St and Victoria St (at this stage 2)
- Culvert installation from 9th Jan 2013
I have represented the Ward in 1995-7 and again from 2006 to the present time. I find being your representative on Council to be very rewarding. Please find out more about current items that I think are of interest as well as my achievements for the Ward and plans for the future.
29 December 2012
Community Update #5; Goodwood Junction
The latest update was released on Fri. The news to be found at;(this is yet to be uploaded) describes the continuing 'early works' programme.